Summary: This article explains the requirements and steps to upgrade a Parker PVplus unit from an LVDT sensor to the new CIP sensor used on Design 47 units. The upgrade requires the correct control module, feedback sleeve, and CIP sensor. After installation, the CIP sensor must be taught and calibrated using the appropriate teach adapter before the pump is returned to operation.
Applies to: Anyone who needs to upgrade an earlier Parker PVplus unit from an LVDT sensor to a CIP sensor.
FINAL ACCEPTANCE CRITERIA
- Correct control module and feedback sleeve installed.
- Properly installed CIP sensor.
- Completed CIP sensor teach/calibration.
- Pump ready for operation.
TECHNICAL BULLETIN
This procedure explains which parts are needed for the upgrade, how to install them, how to teach and calibrate the CIP sensor, and how to confirm that the pump is ready for operation.